What a Kitchen Remodel Costs in Holladay: Real Numbers From a 2026 Proposal

Everyone ends up in the kitchen. In a lot of older homes, the kitchen is also the smallest room on the main floor, with a wall cutting it off from the dining room. You want to open it up, and you want to know what it costs before you start.

Here is a real one we priced in August 2026 in Holladay. The kitchen was 135 square feet, serving a 1,190 square foot main level. We priced three ways to do it, from a new kitchen in the same spot to opening the whole space into one room.

The problem

A 135 square foot kitchen, walled off from the dining room, too small for the way the family gathers.

Option 1: refresh in place

$180,000 to $240,000. Most land near $210,000.

Option 2: open it up

$285,000 to $375,000. Plan around $330,000.

Option 3: whole main level

$330,000 to $430,000. Plan around $380,000.

Not included

Appliances, bought directly by the owners. Installation is included.

Time on site

12 to 16 weeks of construction, after design and selections.

Priced

August 2026, in Holladay.

What the owners wanted

Every gathering landed in the kitchen. Kids at the counter, friends pulling up chairs, and everyone standing right where the cook needed to be. The kitchen was the last room in the house that had never been updated.

They asked for a much bigger island with seating for six to eight, a layout that keeps guests out of the cook's path, deep drawers instead of doors, a coffee bar, and a look that would not feel dated in ten years.

How the work gets done

  1. 1.
    Design and selections

    We turn a 3D scan of the house into two or three floor plan options. The owners pick one, then choose cabinets, counters, tile and lighting with a designer. A structural engineer checks the wall.

  2. 2.
    Lock the design and order cabinets

    Custom cabinets take 8 to 12 weeks to build. Design has to be locked and permits submitted to the city before that clock starts, or the start date slips.

  3. 3.
    Fixed price and schedule

    The ranges turn into one fixed, line-item price. Materials are ordered and the schedule is set before demolition.

  4. 4.
    Demolition with containment

    The work area is sealed off. Air returns are covered with HEPA filters and the space is kept under negative air so dust stays put.

  5. 5.
    Open the wall and build

    For options two and three, the kitchen and dining wall comes out to the engineer's plan, the bay windows are raised to counter height for a cabinet run and coffee bar, and the new kitchen goes in around an island about 10 feet long.

  6. 6.
    Finish

    Counters, backsplash, lighting, plumbing fixtures and appliance installation. In option three, the main-level hardwood is refinished and the fireplace wall is refaced at the same time.

Kitchen before a remodel, with original cabinets and laminate counters
Before: a kitchen we remodeled in Eagle Mountain.
Same kitchen with new cabinets and quartz counters installed
The same Eagle Mountain kitchen with new cabinets and quartz in.

Where the money went

Each option is a range. The low end is a kitchen we would be proud to build. The high end covers premium selections and the surprises an older wall can hold.

OptionWhat is in itRange
1. RefreshFull custom kitchen in the same 135 square feet: cabinets, counters, backsplash, lighting, plumbing in place$180,000 to $240,000. Most land near $210,000.
2. Open it upKitchen and dining wall removed, about 460 square feet made into one room, island seating six to eight, bay window cabinet run and coffee bar, custom cabinets, engineering, permits and structural work$285,000 to $375,000. Plan around $330,000.
3. Whole main levelEverything in option 2, plus the main-level hardwood refinished and the family room fireplace wall refaced$330,000 to $430,000. Plan around $380,000.

Ranges from August 2026. Appliances are bought directly by the owners; installation is in every option. The bay window wall and coffee bar are roughly $25,000 to $30,000 of option 2 and can be left out.

What changes the number

  • Counter material. Quartz holds the range. Quartzite or marble moves it up several thousand dollars.
  • Range size. A 36 inch range or a 48 inch range is the most connected choice in the kitchen. The hood, the makeup air, the cabinet layout and the appliance budget all follow it.
  • The bay window wall and coffee bar. Roughly $25,000 to $30,000. The design works with it or without it.
  • Floors now or later. Refinishing the floors during the remodel costs less than doing it as its own job later, and you only live through the dust once.
  • Island size. Every extra foot is more cabinets and more stone. A prep sink in the island adds plumbing.
  • What is in the wall. If the wall is not holding weight and has no ductwork in it, the structural cost drops. The engineer answers that before demolition.

If your kitchen is too small for how you live

  • Write down where people actually stand when you have company. That tells you what the new layout has to fix.
  • Find out if the wall you want gone is holding weight. A structural engineer can tell you before anyone prices it.
  • Decide your range size early. It sets the hood, the cabinets and the appliance budget.
  • Ask for more than one option. A refresh in place and an open plan can be very different prices.
  • Count backward from when you want it done. Custom cabinets alone take 8 to 12 weeks after the design is locked.

How we handle it

We start with a paid design phase, billed for the work actually done. You see floor plan options first and can stop there. The drawings, engineering and renderings are yours either way. At the end you get one fixed, line-item price that replaces every range.

Kitchen and dining area open to each other with a chandelier
Kitchen and dining as one room in our Parade of Homes build in Hideout.

Common questions

How much does a kitchen remodel cost in Holladay?+

On a Holladay home in August 2026, we priced three options. A full custom kitchen in the same footprint was $180,000 to $240,000, with most landing near $210,000. Opening the kitchen into the dining room around a bigger island was $285,000 to $375,000, planned around $330,000. Doing that plus refinishing the main-level floors and refacing the fireplace wall was $330,000 to $430,000, planned around $380,000.

Does the price include appliances?+

No. The owners buy appliances directly, and installation is carried in every option. The appliance package they described ran $50,000 to $80,000 at retail and tends to net $40,000 to $68,000.

What does it cost to remove the wall between the kitchen and dining room?+

That move is the jump from the first option to the second. Engineering, permits and the structural work are included in the second option. If the wall turns out to be non-bearing and clear of ductwork, the structural budget shrinks. The engineer answers that before demolition.

How long does a kitchen remodel like this take?+

This one was planned for 12 to 16 weeks of construction. Design and selections come first, and custom cabinets take 8 to 12 weeks to build, so design has to be locked well before the start date.

What does the design phase cost?+

We budgeted $15,000, billed time and materials for work actually done. It covers concept floor plans, permit drawings, structural engineering, interior design and selections, and renderings. Hired separately, those typically run $16,300 to $25,500. It ends in a fixed line-item construction price.

Can we live in the house during the remodel?+

Yes. The plan was full dust containment, covered air returns with HEPA filters, and negative air, so the rest of the house stays livable.

Where these numbers come from

The numbers come from Three Peak's preliminary estimate for a Holladay home in August 2026. It was a budget range, not a contract price. Your layout, selections and engineering set your real number.