Most kitchen cost articles quote national averages. They do not tell you much about a kitchen in Park City. So here are numbers from our own work: a Deer Valley kitchen we priced this year, where every dollar went, and the choices that moved the price.
The kitchen
A kitchen in The Oaks at Deer Valley, priced in September 2026. New stone counters, refinished cabinets and island, a new or reworked hood, and appliances.
Option one
About $160,000. Refinish the cabinets and reuse what works: the hood shell, the sink and faucet, and a mid-tier appliance package.
Option two
About $207,000. The full scope: a new hood, a new sink and faucet, and a mix of Wolf and Cove appliances.
Biggest piece
Stone. Five slabs plus fabrication came to about a quarter of the cost of the work.
Time on site
Five to six weeks for that kitchen.
Permit
Not for cabinets and countertops in Park City. Yes for drywall, and usually for electrical and plumbing changes.
Where the money goes
Here is how the cost of the work broke down on the full-scope option for that Deer Valley kitchen.
| Part of the job | Share of the cost |
|---|---|
| Stone slabs and fabrication | 26% |
| Cabinet refinishing and carpentry | 19% |
| Appliances | 12% |
| Electrical and plumbing | 8% |
| Project management | 8% |
| Hood: new insert, surround and plaster | 7% |
| Protection, demolition and haul away | 6% |
| Refinishing four pieces of the owners' furniture | 5% |
| Design | 4% |
| Drywall and paint | 3% |
| Final clean and punch list | 3% |
Shares of the cost of the work, rounded. Permits are billed as they come in and are not in these numbers.
What moved the number
The two options for that kitchen were about $47,000 apart, and none of the difference was in the stone. It came from what was reused and the level of product:
- Reusing the hood shell instead of building a new hood.
- Keeping the sink and faucet.
- A mid-tier appliance package instead of Wolf and Cove. Going all Wolf and Cove would have added about $7,000 more.
- Refinishing one piece of the owners' furniture instead of four.
- One less week on site.
New custom cabinets cost far more than refinishing. On that kitchen, one new run of cabinets above the refrigerator priced at $9,900 to $17,600 by itself.
Stone: the line most people underestimate
Natural stone is bought by the slab, then cut and finished in the shop. On that kitchen, five marble slabs ran about $30,400, and fabrication added $18,650, which works out to about $104 per finished square foot on top of the slabs.
Slabs can be held at the yard while you decide. That hold has a time limit, so the stone pick usually sets the schedule for everything after it. The counters cannot be measured for cutting until the cabinet work is done.
Two kitchens we have built, for comparison
Park City condo: a full kitchen and three bathrooms, finished in four weeks of construction. Walnut-tone cabinets, white quartz, a stacked subway tile backsplash and new vinyl plank floors. Every material was ordered and staged two weeks before demo.
Eagle Mountain main floor: a full kitchen gut with new cabinets, quartz and a subway tile backsplash, plus new floors and paint through the main level. No walls moved and no major plumbing or electrical changes. It came in at about $60,000 with change orders, which shows how much a valley job with a simpler finish level can differ from a mountain kitchen.


How to budget for your kitchen
- Decide early whether the cabinets stay. Refinishing versus new cabinets is the biggest fork in the road.
- Pick the stone first. It is the biggest single line and it drives the schedule.
- Know which appliances you want before the cabinet drawings are final.
- Count the extras: hood, lighting, furniture, a coffee bar. Each one is its own line.
- Leave room for permits, and for anything found behind the walls.
How we price a kitchen
We walk the kitchen with you, scan it, and give you two clear options: one that reuses what makes sense, and one with everything you asked for, written as a ceiling. Each option is one number with a list of what is in it, and a short list of what is not.
Common questions
How much does a kitchen remodel cost in Park City?+
A kitchen in The Oaks at Deer Valley that we priced in 2026 came to about $160,000 when the cabinets were refinished and some items were reused, and about $207,000 for the full scope with a new hood, sink and appliances. Both included new stone counters.
What is the biggest cost in a kitchen remodel?+
On that kitchen, stone was the biggest single piece: five slabs plus fabrication came to about a quarter of the cost of the work. Appliances and cabinet work were next.
Is it cheaper to refinish cabinets than replace them?+
Usually, yes. On that kitchen, refinishing the existing cabinets and island was part of both options. One run of new custom cabinets above the refrigerator priced at $9,900 to $17,600 by itself.
How long does a kitchen remodel take?+
That Deer Valley kitchen planned for five to six weeks on site. Our Park City condo job did a kitchen and three bathrooms in four weeks, because every material was ordered and staged two weeks before demo.
Do I need a permit for a kitchen remodel in Park City?+
Not for new cabinets or countertops. Any drywall work needs a permit, and electrical and plumbing changes usually do too.
Why do mountain kitchens cost more than valley kitchens?+
Travel and access, working around snow and HOA rules, and higher finish levels. For comparison, our Eagle Mountain main-floor job, a kitchen gut plus new floors and paint with no walls moved, came in at about $60,000.
Where these numbers come from
The Deer Valley numbers come from a Three Peak estimate written in September 2026. The Eagle Mountain number is that job's final price with change orders, from our records. Every kitchen is different, so your walkthrough and your estimate set your real number. Permit rules were checked with Park City in October 2026.