What a Single-Level Home Addition Costs: A Real Francis Proposal, Room by Room

You need more room, but you do not want to move, and building up may not work for your house. So you build out: a new primary suite, another bedroom, a laundry room on the main floor. The question is what all of that really costs.

Here is a real one we priced in August 2026 in Francis, Utah. It is a main-level addition on a new crawl-space foundation, with a deck, tied into the existing house. The proposal broke the price out room by room, so you can see exactly where the money goes.

The project

A main-level addition: primary bedroom, primary bath, toilet room, primary closet, bedroom, play room, laundry, hallway and a Trex deck.

Total proposal

$545,300.90

Shell (foundation, framing, roof, exterior, deck)

$385,923.80

Not included

Electrical service or panel upgrades, new HVAC equipment, repairs to old utilities, decorative timber and hidden conditions.

Time on site

The proposal did not set a number of weeks.

Priced

August 2026, in Francis, Utah.

What the owners wanted

The goal was a real primary suite and more rooms on the main floor. The plans added a primary bedroom with its own bath, toilet room and closet, a second bedroom, a play room and a laundry room, plus a deck and a covered outdoor area.

The addition had to look like it was always part of the house. The roof slopes and exterior finishes were matched to the existing home where they meet.

How the work gets done

  1. 1.
    Set up and open the house

    Temporary toilet, dumpster, protection for the driveway, patio and existing house, and careful demolition where the addition connects.

  2. 2.
    Dig and pour

    Excavate the crawl space, pour footings and foundation walls to the engineer's plans, waterproof the walls, add insulation and a vapor barrier, then backfill and grade the soil away from the house.

  3. 3.
    Frame and dry in

    Floor framing, walls, beams and shear walls, then trusses set by crane. Asphalt shingles, with ice and water shield at the eaves and valleys, soffit, fascia and gutters, vinyl windows, stucco and painted board and batten siding.

  4. 4.
    Rough in

    Plumbing for the new bath, toilet room and laundry. New circuits, lights, outlets and smoke and CO detectors. New ductwork and registers tied into the existing furnace. Bath fans and dryer vents run outside.

  5. 5.
    Insulate and finish

    R-66 blown insulation in the ceilings, drywall, interior doors and trim, paint, carpet in the bedrooms and tile in the wet areas. Custom base cabinets and solid-surface tops in the bath and laundry.

  6. 6.
    Deck

    Deck framing and stairs with Trex decking and hidden fasteners, and a custom steel railing with a black powder-coat finish.

New concrete footings with rebar for an addition foundation
Footings on our second-story addition in Francis. Every addition starts with foundation work like this.
Tile being set over a waterproof membrane in a new bathroom
Bath tile going down on our second-story addition in Francis.

Where the money went

This proposal was priced room by room. The shell line holds everything outside and structural. Each room line holds what it takes to finish that room.

SectionTotal
Project-wide and addition shell (general conditions, excavation, foundation, framing, crane, roof, stucco, siding, windows, fixture allowances, deck)$385,923.80
Primary bath$43,770.89
Laundry room$19,710.04
Primary bedroom$18,984.91
Play room$17,377.49
Primary closet (with washer and dryer hookups)$12,379.40
Bedroom$12,238.95
Existing primary bedroom (updated)$12,011.87
Hallway$10,215.19
Toilet room$7,705.92
Existing primary closet$1,934.98
Bedroom closet$1,750.00
Shower (drywall and insulation)$1,297.46
Total$545,300.90

Proposal from August 2026, priced from the architectural and structural plans. Permit fees were carried as an estimated allowance.

What changes the number

  • The foundation. A crawl space needs digging, footings, walls and insulation. Rock, groundwater or poor soil found while digging is extra.
  • Your electrical panel. This price added circuits to the existing panel. If the panel or service is too small, the upgrade is extra.
  • Your furnace. This price tied new ducts into the existing system. If it cannot heat and cool the added rooms, new equipment is extra.
  • Finishes. Shower tile was budgeted at $5.50 per square foot for the material. Bigger tile budgets, wood floors instead of carpet, or a different counter all move the number.
  • Exterior match. Stucco and board and batten were priced here. Stone, timber accents or a different roof would change it.
  • The deck. Trex with a steel railing was priced here. A bigger deck or a different railing changes it.

If you are thinking about an addition

  • Get plans drawn and engineered before you ask for prices. Then every builder prices the same thing.
  • Find out how big your electrical panel is and how old your furnace is. Those two answers can add real money.
  • Ask for the price room by room. It shows you where to trim if the total is too high.
  • Ask what is not included, in writing. Hidden conditions and utility upgrades are where budgets get surprised.
  • Compare building out to building up. The money lands in different places.

How we handle it

We price additions from the engineered plans, room by room, and we write down what we are assuming about your existing panel, furnace and utilities. If something hidden shows up once we dig or open a wall, we stop and give you a written change order before we go on.

Common questions

How much does a single-level home addition cost?+

Our August 2026 proposal for a main-level addition in Francis, Utah came to $545,300.90. It added a primary bedroom, primary bath, separate toilet room, primary closet, a bedroom, a play room, a laundry room, a hallway and a Trex deck with a steel railing, all on a new crawl-space foundation.

Where does most of the money go in an addition?+

The shell. Foundation, framing, roof, siding, stucco, windows, the deck and general conditions came to $385,923.80 of the $545,300.90. The finished rooms inside made up the rest.

What does a new primary bathroom cost inside an addition?+

In this proposal the primary bath was $43,770.89. That covered tile floors, a tiled shower to the ceiling, a frameless glass door, custom base cabinets, a solid-surface top, plumbing for two sinks, a shower, a tub and a toilet, plus drywall, insulation, doors, trim and paint. The tub, the faucets and the light fixtures were priced in the shell line, not here. The separate toilet room was another $7,705.92.

Is a single-level addition cheaper than adding a second story?+

It depends on the house. This single-level addition needed its own new foundation, roof and deck, and most of the price was in that shell. Our second-story addition cost guide shows how a different kind of addition breaks down.

What was not included?+

Any electrical service or panel upgrade, any new furnace or air conditioning equipment if the existing system cannot carry the added rooms, repairs to old plumbing or utilities, decorative timber, and anything hidden that could not be seen before digging or opening walls. Those are handled by written change order.

Does the addition use the home's existing furnace and electrical panel?+

That was the plan. New circuits were added to the existing panel and new ducts tied into the existing furnace. Neither had been load-checked yet, so an upgrade, if needed, would be extra.

Where these numbers come from

The numbers come from Three Peak's proposal for a home addition in Francis, Utah in August 2026. Every addition is different, so your plans, your site and your selections set your real number.